/*! This file is auto-generated */ .wp-block-button__link{color:#fff;background-color:#32373c;border-radius:9999px;box-shadow:none;text-decoration:none;padding:calc(.667em + 2px) calc(1.333em + 2px);font-size:1.125em}.wp-block-file__button{background:#32373c;color:#fff;text-decoration:none} Q4OQ Always Rain Irrigation, Inc., wo... [FREE SOLUTION] | ÷ÈÓ°Ö±²¥

÷ÈÓ°Ö±²¥

Always Rain Irrigation, Inc., would like to determine capacity requirements for the next four years. Currently, two production lines are in place for making bronze and plastic sprinklers. Three types of sprinklers are available in both bronze and plastic: 90-degree nozzle sprinklers, 180-degree nozzle sprinklers, and 360-degree nozzle sprinklers. Management has forecasted demand for the next four years as follows:

Yearly Demand

1 (IN 000s)

2 (IN 000s)

3 (IN 000s)

4 (IN 000s)

Plastic 90

32

44

55

56

Plastic 180

15

16

17

18

Plastic 360

50

55

64

67

Bronze 90

7

8

9

10

Bronze 180

3

4

5

6

Bronze 360

11

12

15

18

Both production lines can produce all the different types of nozzles. The bronze machines needed for the bronze sprinklers require two operators and can produce up to 12,000 sprinklers. The plastic injection molding machine needed for the plastic sprinklers requires four operators and can produce up to 200,000 sprinklers. Three bronze machines and only one injection molding machine are available. What are the capacity requirements for the next four years? (Assume that there is no learning).

Short Answer

Expert verified

The capacity requirement for the next four years is the same as first-year = 6, 30,000.

Step by step solution

01

Capacity requirement

It refers to the amount of knowledge or resources that a product or system can manage. All of these are critical because they define how the system may be utilized is namedcapacity requirement.

02

Calculating the capacity requirement for the following 4 year

Given,

Bronze machines have 3 lines and another one has 2 lines

Total machines of bronze = 3 x 2

= 6 machines.

Sprinklers produced per each sprinkler = 12000 units.

1st-year calculation of bronze sprinkler

= Total machines of bronze x produced sprinklers

= 6 x 12,000

= 72,000

Types of sprinklers available in bronze are:

90000, 180000, 360000

Where,

1st year of bronze machines

= 90000+180000+360000

= 6, 30,000

6, 30,000 are for less than 1st year.

Bronze is presenting the 1-year value determined over 4 years.

= 72000 x 4

= 2, 88,000 units

Given,

The plastic units can produce up to 2, 00,000 sprinklers.

Where plastic sprinkler has 1 line and another one has 2 lines

Hence, plastic line = 1 x 2

= 2

1st-year calculation of plastic sprinkler

= Plastic line x plastic unit produced

= 2 x 2, 00,000

= 400,000

Plastic is presenting the 1-year value determined over a period of 4 years.

= 4th-year x plastic sprinkler of 1set year

= 4 x 400,000

= 1, 60,000 units.

The capacity requirements for the subsequent four years of the bronze machine are going to be the same as the first year i.e., 6, 30,000.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with ÷ÈÓ°Ö±²¥!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

A fast-food restaurant serves hamburgers, cheeseburgers, and chicken sandwiches. The restaurant counts a cheeseburger as equivalent to 1.25 hamburgers and chicken sandwiches as 0.8 hamburger. Current employment is five full-time employees who each work a 40-hour week. If the restaurant sold 700 hamburgers, 900 cheeseburgers, and 500 chicken sandwiches in one week, what is its productivity? What would its productivity have been if it had sold the same number of sandwiches (2,100), but the mix was 700 of each type?

There is an 82 percent chance the project below can be completed in X weeks or less. What is X?

Match the following OSCM job titles with the appropriate duties and responsibilities.

Plant manager A. Plans and coordinates staff activities such as new product development and new facility location.

Supply chain manager B. Oversees the movement of goods throughout the supply chain.

Project manager C. Oversees the workforce and resources required to produce the firm’s products.

Business process improvement analyst D. Negotiates contracts with vendors and coordinates the flow of material inputs to the production process.

Logistics manager E. Applies the tools of lean production to reduce cycle time and eliminate waste in a process.

Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and bring in \(25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity completed. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that, even though we should have 83 percent (25y30) of this activity complete, it is only 50 percent complete. This part of the project was scheduled to bring in \)150,000 in donations. The final activity is for matching funds. This activity is scheduled to run for the last 10 days of the project and has not started. It is scheduled to bring in an additional \(50,000. So far \)175,000 has been brought in on the project. Calculate the schedule variance, schedule performance index, and cost (actually value in this case) performance index. How is the project going? Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.

Do the concepts of complexity and divergence apply to an online sales company such as Dell Computer?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.